QC Run - 2/4/2026 / QC Report
Generated on February 4, 2026
TOTAL ISSUES
14
CRITICAL
2
Must fix before issuance
MAJOR
7
OVERALL SCORE
71%
Detailed Issues
Egress path not continuous to exit
A-102Page 8CRITICALEgress from Room 102 passes through another tenant space before reaching exit.
Recommended Fix:
Provide dedicated egress or revise separation per IBC Ch. 10.
Toilet room clear floor space under 30" x 48"
A-104Page 14CRITICALLavatory does not show 30" x 48" clear floor space per ADA 606.2.
Recommended Fix:
Adjust fixture layout or provide clear floor space per code.
Dimension string does not close
A-301Page 16MAJORExterior wall dimension on A-301 is missing one segment; total does not match grid.
Recommended Fix:
Add missing dimension or correct total to match grid.
Door schedule inconsistency
A-602Page 18MAJORDoor 204C is in door schedule on sheet A-602 but not shown on floor plan sheet A-102.
Recommended Fix:
Add door 204C to floor plan or remove from schedule; align schedule and plans.
Wall type baseline conflict (A-102 vs A-103)
A-102Page 18MAJORA-102 general notes state "All walls S04E unless noted"; A-103 states "All walls S03E unless noted." Conflict can cause incorrect wall construction.
Recommended Fix:
Confirm intended typical wall type and revise A-102/A-103 notes so they are consistent.
Wall type inconsistent between floor and dimension plan
A-103Page 18MAJORTypical wall type differs between floor plan (S04E) and dimension plan (S03E) notes.
Recommended Fix:
Align typical wall type in both plan notes.
Code edition mismatch
A-103Page 19MAJORDimension plan legend references 2018 IBC (e.g. Sections 509, 707). Adopted code for the project is 2021 IBC.
Recommended Fix:
Update sheet legends to 2021 IBC and confirm section numbers remain correct.
Wrong jurisdiction in roof plan note
A-301Page 21MAJORRoof plan note requires "Town of Gilbert" approval for RTU visibility. Project is Riverside, CA—likely template carryover.
Recommended Fix:
Replace with correct AHJ (Riverside, CA) or remove; use project-specific AHJ only.
Door schedule rating vs comment conflict
A-602Page 34MAJORDoor 205A shows "1-HOUR RATED" in assembly column but comment says "2Hr Rated Door." Internal conflict with suite separation requirements.
Recommended Fix:
Confirm required fire rating and revise schedule so rating and comments match; verify hardware.
Door schedule references missing hardware sheets
A-602Page 34MAJORA-602 note "REFER TO A-606, A-607 FOR HARDWARE SCHEDULE" but A-606 and A-607 are not in the set.
Recommended Fix:
Include A-606/A-607 in the set or correct the note to actual sheet locations.
Symbol legend missing for custom symbols
A-103Page 5MINORCustom symbols on A-103 are not defined in legend.
Recommended Fix:
Add symbol legend on cover or discipline sheet.
Detail reference bubble points to wrong sheet
A-202Page 11MINORDetail 4/A-202 references S-402 but detail is on S-401.
Recommended Fix:
Correct detail reference to S-401 or move detail.
Corridor assembly does not comply with IBC
A-201Page 18MINORCorridor wall at grid B not labeled per IBC; may not meet required rating.
Recommended Fix:
Verify and label fire rating per IBC Table 1020.1.
Roof plan keynotes have placeholder/blank items
A-301Page 21MINORRoof plan keynote list includes blank or placeholder entries; set is incomplete.
Recommended Fix:
Complete keynote set and remove placeholders before issuance.
Cross-sheet reference to missing sheets
A-602Page 34MINORSchedule references hardware sheets A-606/A-607 which are not in the set.
Recommended Fix:
Add referenced sheets or update note to match sheets provided.